The work
Special repair & missing pole fittings and cable laying for illumination of dark-spot women-safety pin underdeck flyover light at various roads under AE (E)-III, R.K. Puram, New Delhi.
Electrical installation — pole fittings, cable laying, underdeck flyover lighting.
- Start
- 27 December 2020
- Stipulated completion
- 26 March 2021
- Actual completion
- 17 August 2022
- Extension of time
- —
- Compensation
- Nil
- Litigation / arbitration
- None
Department
PWD Delhi
Electrical Division South-West, New Delhi